008613695863502
Home / News / Content

Aug 11, 2021

How To Pave The Artificial Turf Football Field?

How to use artificial turf to lay a football field?


Tools/Materials:

artificial turf

Quartz sand

Rubber granules

glue

Seam cloth

brush

Wallpaper knife

Rubber hammer

Method/step:


1. Check the entire turf field to be laid, and whether the foundation density and flatness meet the requirements, and then start paving the artificial turf. In order to allow the folds of the lawn to expand and contract naturally, it is best to put the artificial lawn in the sun for a day.



 2. Before starting to pave the artificial turf, measure and set out the entire field, determine the position of the field line and mark it, mark it with different colors of ink, and determine the direction and position of the artificial turf.



3. Start laying artificial turf: Install a special splicing belt on the joint surface of the turf, and fix it with steel nails. The head of the steel nails must not be raised, and the joint area must be overlapped by more than 10cm.



4. Apply glue on the joint interface. Before the glue dries, pave and join the cut lawns so that each piece of artificial turf is tightly bonded.



5. After the paving is completed, it is necessary to carefully check whether the bonding of each joint area is smooth and whether the adhesion of the artificial grass is firm. After checking that all items meet the requirements, the construction of the next process can be carried out.



6. Cut the green artificial turf at the position where the white artificial turf needs to be inserted, insert the connecting tape, and apply glue on it, and then insert the cut white artificial turf into the line marked before paving The position is bonded with the splicing tape.



7. Sprinkle quartz sand and colloidal particles according to the needs of the site. If you need to sprinkle quartz sand, pour the quartz sand or black rubber particles into the sprinkler. Push the sprinkler to fill the surface of the artificial turf. The brush behind the sprinkler brushes the quartz sand or black. Rubber particles, and make the quartz sand or black rubber particles fall sufficiently. The speed of pushing the granulator must be uniform, not too fast or too slow to make the thickness uniform.



  9. After the quartz sand or rubber granules are laid, check whether they are level and sufficient. Insufficiencies need to be supplemented as needed. Any impurities found in the paving should be removed immediately to ensure quality.



 10. The quartz sand or rubber particles in the paving should be kept dry to facilitate the flow of the quartz sand or rubber particles in the paving. After the quartz sand or rubber particles are laid, a hard brush or a light-duty drag-type heavy brush can also be used to pave back and forth to make the quartz sand fall fully and densely.



 11. After the laying is completed, check and accept and exit the site.



Precautions

1. Gluing: It is required to apply a brush to the back of the turf with a uniform thickness, and do not apply the glue repeatedly, otherwise, it will foam or even fall. When applying glue on the base cloth, strictly control the thickness of the glue, pay attention to the proper speed of glue application, and apply the glue on the two bonding surfaces to be bonded respectively.

2. Adhesion: According to the actual influence of the temperature, humidity, air pressure, and other conditions at the time, the drying time should be reasonably controlled. Generally, the glue should reach 80% to 90% dry within 10-30 minutes after the glue is applied. It is advisable to touch the glue without sticking. When bonding, it is required to align and stick firmly at one time, and must not move the bonded object back after bonding.

3. Pressurization: After bonding, remove the debris on the surface, use a special rubber hammer to hammer hard from the bonding point to both sides, so that the surface is fully contacted and dense, and the bonding is stronger.